Key dates
2018
Announced as a winner of the Sustrans Community Links PLUS funding initiative.
2019
Public engagement along the route
- Public drop-ins
- Key stakeholders workshop
- Community councils meetings
- Developing concept design proposals
2020 – 2021
Project Development
- COVID-19 Pandemic. Project underwent scope revision and adjustments
- Design alterations finalised
2022 – 2024
Technical design
- Design details finalised for construction
- Site investigation
- Traffic orders advertised and completed
- Pre-construction starts
2025
Phase 1 construction begins
Regular project updates throughout
2026
Construction
- Phase one complete
- Proposed start for future phases.