The Capital Strategy 2026/ 36

Capital Investment Programme

The General Fund Capital Budget 2026-2036, as amended by the budget meeting of 26 February 2026, sets out priorities for £2.6bn of Council capital investment, in alignment with the Council Business Plan, over the medium to long-term. Of that investment:

  • £1,349 (52%) has ringfenced funding with conditions attached to grants, capital receipts or developer’s contributions, or relates to prudentially funded projects. This includes acquisition of housing for temporary accommodation prudential borrowing, transfer of affordable housing grant to housing projects, and On-lending to Edinburgh Living for the acquisition of mid-market rent homes from the HRA.
  • £516m (20%) is contractually committed on the Learning Estate (£476m); with works underway on new schools and extensions; to works on Council Buildings (£20.3m); Roads and Transport Infrastructure including North Bridge Refurbishment (£14.3m), and Cultural Projects (£5m).
  • £694m (27%) is uncommitted and currently allocated in the form of budgets to support capital works on the Learning Estate, Roads and Transport Infrastructure, Land and Building Improvements, Disability Adaptations in Private homes, Digital Investment and Edinburgh Leisure.

Significant General Fund capital projects through the 2026-36 programme include:

  • Housing and Homelessness £1,355m, including grants for new affordable housing, On-lending to Edinburgh Living for the acquisition of mid-market rent housing and to acquire units to be retained by the Council for use as temporary accommodation.
  • Learning Estate - £513m included for 6 new primary schools, 3 primary school extensions, 4 new secondary schools, 4 secondary school extensions and for significant investment in the learning estate and special schools as part of the Inclusive Learning Strategy.
  • Building improvement programme - £223m to meet the objectives of the Corporate Property Strategy.
  • Investment in Roads and Transport Infrastructure (including Tram Lifecycle renewals) - £347m

The Housing Revenue Account (HRA) Budget Strategy 2026/27 to 2035/36 sets out priorities for £2.9bn of HRA capital investment based on tenant priorities, service performance and statutory investment requirements. The programme is to be funded from HRA borrowing, Scottish Government grant funding for new affordable homes and capital receipts. Based on current financial assumptions; including an annual 7% rent increase to 2033-34, all existing Council homes could be brought up to the Energy Efficiency Standard for Social Housing (EESSH2) over the lifetime of the Business Plan and 4,602 new Council homes could be delivered.

The investment programmes include a significant intervention to address the Housing Emergency, creating 5,900 additional settled and temporary accommodation within the Edinburgh over the next five years, over and above the existing new homes development programme.

In total, for the period 2026-36, the Council is planning total capital expenditure across the General Fund, HRA and Leases of £5.5bn.

The investment is phased to reflect deliverability, funding availability and affordability within the Medium-Term Financial Plan. The Council does not rely on speculative income assumptions, so the Capital Programme is prudent, and any further funding will provide an opportunity for additional investment or to reduce borrowing.

The Capital Programme is fully funded over the 10-year period. However, if a funding gap in the strategy emerges through failure to deliver revenue savings, increased borrowing costs or project cost pressures increase, then further re-profiling of priorities, reduction in scope of projects or additional revenue savings to fund the borrowing costs to deliver the Capital Budget Strategy will be required ahead of future budget setting to comply with the terms of the Prudential Code. This could potentially mean that later phases of the programme could not be delivered within the ten-year strategy.