We’re improving the road surface, crossing facilities at junctions and drainage at Restalrig Road, Restalrig Road South and Blackie Road, which includes road resurfacing and pavement works at junctions.
The work will improve driving and walking conditions and enhance road safety.
Working in stages
Work will be done in nine stages starting from 9 March 2026. Sometimes stages may overlap.
We expect work to end in July 2026.
Our contractor will work Monday to Friday, typically between 7am and 7pm.
We will stop work during the Easter break from 3 April to 12 April.
During each phase there will be pavement and drainage work where we'll use parking suspensions, lane closures and temporary traffic lights at junctions.
Project updates
14 April 2026
We are currently repairing pavements and drainage near Restalrig Circus (Phase 5) under temporary traffic lights. It is estimated that all pavement and drainage works will be completed by mid-May 2026.
Road resurfacing begins on Monday 20 April 2026, starting at the north end of Restalrig Road at the East Hermitage Place junction (Phase 1). To keep the area safe, we will close the road in phases, with all resurfacing expected to be finished by mid-July 2026. This means vehicles cannot drive through Restalrig Road, and traffic will be diverted via Lochend Road and Sleigh Drive.
To help with waste collection, communal bins will be relocated at the end of each phase. If you live on a cul-de-sac, you can access your street outside of working hours (before 7.30am and after 5pm). For information on bus diversions, please check your bus provider’s website.
Phase 1 - Restalrig Road from East Hermitage Place to Cornhill Terrace.
Estimated 3 weeks
Pavement works and drainage - parking suspensions, side road closures (East Restalrig Terrace, Blackie Road and Cornhill Terrace) and temporary traffic lights.
Road resurfacing - road closure 24/7, Traffic diversion via Lochend Road
Phase 2 - Restalrig Road from Cornhill Terrace to No.88 Restalrig Road
Estimated 3 weeks
Pavement works and drainage - parking suspensions, side road closures (Ryehill Terrace) and temporary traffic lights
Road resurfacing - road closure 24/7, traffic diversion via Lochend Road.
Phase 3 - Restalrig Road from No.88 Restalrig Road to Prospect Bank Gardens
Estimated 3 weeks
Pavement works and drainage - parking suspensions, side road closures (Prospect Bank Road) and temporary traffic lights.
Road resurfacing - road closure 24/7 with local access to Easter Hermitage and Prospect Bank Gardens via Restalrig Road outwith the site working hours 7.30am and 5pm. Traffic diversion via Lochend Road.
Phase 4 - Restalrig Road from Prospect Bank Gardens to Alemoor Park
Estimated 3 weeks
Pavement works and drainage - parking suspensions and temporary traffic lights.
Road resurfacing road closure 24/7 with local access to private access road via Restalrig Road outwith the site working hours 7.30am and 5pm. Traffic diversion via Lochend Road.
Phase 5 - Restalrig Road from Alemoor Park to No.167 Restalrig Road
Estimated 3.5 weeks
Pavement works and drainage - parking suspensions, side road closures (Restalrig Circus) and temporary traffic lights.
Road resurfacing - road closure 24/7 with local access to Alemoor Park via Restalrig Road outwith the site working hours 7.30am and 5pm. Traffic diversion via Lochend Road.
Phase 6 - Restalrig Road from No.167 Restalrig Road to Restalrig Crescent
Pavement works and drainage - parking suspensions and temporary traffic lights.
Road resurfacing - road closure 24/7 with local access to Restalrig Park via Restalrig Road outwith the site working hours 7.30am and 5pm. Traffic diversion via Lochend Road.
Phase 7 - Restalrig Road South - From Restalrig Crescent to Restalrig Square
Pavement works and drainage - parking suspensions, side road closures (Restalrig Crescent and Lochend Avenue) and temporary traffic lights.
Road resurfacing - road closure 24/7, traffic diversion via Lochend Road.
Phase 8 Restalrig Road South - From Restalrig Crescent to Restalrig Square
Pavement works and drainage - parking suspensions and temporary traffic lights.
Road resurfacing - road closure 24/7 with local access to Restalrig Square and St. Margarets Apartments via Restalrig Road South outwith the site working hours 7.30am and 5pm Traffic diversion via Lochend Road.
Phase 9 Blackie Road - From Summerfield Gardens to Claremont Road
Pavement works and drainage - parking suspensions and temporary traffic lights.
Road resurfacing - road closure 24/7, Traffic diversion via: Claremont Road – Claremont Park – Restalrig Road.
Access
- Pedestrians will be able to access the area at all times.
- Restrictions will be in place for vehicles at times during road resurfacing, apart from emergency vehicles which will have access at all times.
- We will use temporary parking restrictions to make sure the work is done safely, with signs showing details of specific restrictions.
- We will have a Council officer on-site during the work to monitor progress and provide assistance and information to residents and businesses.
Further information
We understand that the work will be disruptive and want to thank you for your patience and understanding.
Every effort will be made to accommodate residents and businesses and we hope that you will appreciate the long-term benefits and improvement the project will deliver.
If you have any specific queries, please do not hesitate to contact the site team directly or email us at transport.designservice@edinburgh.gov.uk