Latest news
Melville Crescent Public Realm
With the cycleway along Melville Street complete we are now continuing with the planned public realm work to the Melville Crescent diamond.
-
Roseburn Terrace/Russell Road junction
We will be carrying out remedial work to the roads and pavements around the Roseburn Terrace/ Russell Road junction to ensure long term quality and public safety.
-
Walker Street North
As part of the Melville Crescent works, we wanted to update all Walker Street North residents and businesses that the street will closed from 24 April for about nine months.
-
Queensferry Street junction and Randolph Place
Update on works planned at Randolph Place to rectify a ponding issue and a collapsed manhole cover at the Queensferry Street junction.
-
Haymarket Junction
We wanted to update you on our work at Haymarket junction. The taxi call forward system has been successfully installed, and we have re-opened the Haymarket Station taxi rank.
-
Haymarket Station - new taxi rank
As part of our City Centre West to East Link project, we are introducing a new taxi rank at the current drop-off area in front of Haymarket Station.
-
A8 Final Remedial Works - Roseburn Terrace and West Coates
We are carrying out remedial work to the raised tables at the Wester Coates Road junction and plan to complete this work by 9 February.
-
CCWEL Project Update - December 2023
Welcome to the City Centre West to East Link (CCWEL) newsletter with information and updates on project activity and planned work.
-
Magdala Crescent Closure
We can now share a further update about the reconstruction of the road at the bottom of Magdala Crescent.
-
Wester Coates Road - Remedial Works
You may be aware of cracks on the raised table slabs at the junction of Wester Coates Road and the A8 West Coates.