Additional Traffic Management Arrangements as of 6 April 2021

Weekly Traffic Management

Please find below a summary of additional traffic management arrangements to accommodate site investigations works and utility diversions outside the main area of works.

Traffic management arrangements for the main area of works are available to view and download.

LEITH WALK

Elm Row – Temporary Parking Restrictions - WORKS CANCELLED

These works have now been cancelled and are not required to be undertaken.

We will be carrying out ground penetrating radar (GPR) surveys in the cobbled area on Elm Row from Monday 12 April for approximately 5 days. To facilitate these works we are required to temporarily restrict parking to the East side of the cobbled area on Elm Row. 

View more information on the Elm Row parking restrictions.


McDonald Road Closure 

From Saturday 27 March McDonald Road junction with Leith Walk will close to traffic. This is to facilitate main infrastructure works on Leith Walk. Local diversions will be in place.

View the updated Leith Walk London Road to Annandale Street traffic management plan (PDF). 


Annandale Street to Balfour Street - Cycleway Adjustments 

In order to create the segregated cycle lane on Leith Walk sections of the cycle between Pilrig Street and Dalmeny Street to accommodate the works. While these works are being carried out there will be restrictions in in place for cyclists. Where possible, alternative routes will be signposted for cyclists, however there may be instances when this is not possible. 

Find out more information on the Leith Walk cycle lane adjustments. 


Road Closure – Springfield Street / Road Opening – Stead’s Place
 
Access and egress to Springfield Street from Leith Walk will be closed from Tuesday 26 January.  Traffic will be diverted via Stead’s Place which will be opened to facilitate the closure.
 
Download the Springfield Street / Stead's Place traffic management plan (PDF). 


Jane Street at Jane Street Industrial Estate - Temporary Road Closure - UPDATE

Works have commenced on the reinstatement of the cobbles on Jane Street within the current Road Closure.  These works are anticipated to take 4-6 weeks.  The Road Closure will remain in place to accommodate the reinstatement.

Pedestrian access and vehicle access to businesses will be maintained at all times.

Download the Jane Street temporary road closure traffic management plan (PDF)


Manderston Street – Temporary Road Closure

Due to the complexity of the 500mm diameter gas diversion works on Manderston Street / Leith Walk the Road Closure on Manderston Street has been extended until May 2021.  Localised diversions and parking restriction will be in place with pedestrian access being maintained at all times.

Download the Manderston Street traffic management drawing (PDF)

 

Croall Place - Adjustments to Footpath 

We are required to undertake site investigation works on the footpath at Croall Place between McDonald Road and the large digital advertising screen. These works will commenced on Wednesday 31 March for 2 weeks. This will result in the footpath width being reduced and the temporary bi-directional cycleway being closed. Signage advising of this closure will be in place.


Lorne Street – Temporary Road Closure

There will be no access to Leith Walk from Lorne Street from Tuesday 6 April for approximately 5 days. Access will be maintained via Leith Walk which will also include access to Lorne Place. Pedestrian access will be maintained however parking will be restricted for the duration of the closure. 

Download the Lorne Street traffic management plan (PDF).

 

FOOT OF THE WALK TO NEWHAVEN 

Baltic Street Junction – Temporary Traffic Lights - UPDATE these arrangements have been delayed to Wednesday 17 March

The carriage way at Bernard / Baltic Street junction will be reduced to one lane traffic, controlled by temporary traffic lights. This will be in place from Wednesday 17 March (previously 15 March 2021) for approximately 12 weeks.

Download the Baltic Street junction traffic management plan (PDF). 


Lindsay Road - Traffic Management Adjustments 

From Monday 29 March works will start on the south side of Lindsay Road. To accommodate these works the traffic management arrangements will be adjusted in the area. Local diversions for pedestrians and motorists will be in place. These new arrangements are expected to be in place until mid-May. On completion traffic management arrangements will flip back to the north side of Lindsay Road to continue with main infrastructure works. 

Download the Lindsay Road traffic management plan (PDF). 


Traffic Management Adjustments at Constitution Street/Ocean Way junction with Tower Street

We will be revising the current traffic management arrangements at the Constitution Street/Ocean Way junction with Tower Street to include an additional traffic light head at Constitution Place, changing the current 3-way set up to 4-way. This will be in place from Monday 29 March 2021 to further progress the works in this area.

View the updated traffic management plan for Constitution Street/Ocean Way (PDF). 


Mitchell Street – Road Closure

We will be closing vehicle access to Maritime Lane from Mitchell Street on Wednesday 7 April. This closure is to progress track works across the junction and is expected for up to 10 weeks. A  temporary pedestrian walkway connecting both sides of the street between Queen Charlotte Street and Mitchell Street / Maritime Lane will be created over the coming week.

You can view the Mitchell Street temporary traffic management arrangements here (PDF).


Foot of the Walk to Laurie Street – Tram Stop Works

On Tuesday 6 April works will commence to construct the tram stop between the Foot of the Walk / Laurie Street. These works require closure to the east side of the foot way. Local diversions for pedestrians will be in place.

Published: 6th April 2021