Foot of the Walk

Works in the Foot of the Walk section started in November 2021. See when works are expected to finish in this section.

Traffic Management

UPDATE: traffic management and site setup will change from the weekend of 3/4 December to progress project works. Read more details here.

Site and traffic management changes have been made at the Foot of the Walk in order to complete works. These were introduced over the weekends of 22/23 October and 29/30 October 2022 and will remain in place until the end of works.

Under these arrangements:

  1. During Phase One (22 and 23 October 2022) site arrangements will move from east to west between Foot of the Walk and Crown Place.
  2. The Manderston Street / Leith Walk junction remains open to traffic travelling from Easter Road to Leith Walk. Vehicles will only be allowed to turn left onto Leith Walk heading towards the city centre.
  3. The left-hand turn from Duke Street onto Leith Walk will be re-introduced.
  4. There will be no access to Manderston Street from Leith Walk. 
  5. Traffic will continue to be able to turn right from Great Junction Street onto Leith Walk.
  6. Traffic movements between Great Junction Street and Duke Street heading both ways will remain under two-way traffic management.
  7. Site lines will be extended on Duke Street heading east. The pedestrian crossing point will remain in place, however, will move throughout the phasing of these works to accommodate associated works.
  8. The pedestrian crossing point on Great Junction Street will be temporarily reinstated, however, will move throughout the phasing of these works to accommodate associated works.
  9. Alternative diversions will be in place which will be signposted. 
  10. During Phase Two (29 and 30 October 2022) site arrangements will move from the east side of Leith Walk to the west side of Leith Walk, between Crown Place to Jane Street.
  11. Pedestrian access to properties will remain in place at all times.

Traffic management plans can be found below in the Downloads section.

 

Parking and access

Parking enforcement will remain in place on Great Junction Street, Manderston Street and Gordon Street to accommodate the diversion route. 

Lothian Buses

Bus stops will remain in place on Leith Walk.  Details of any bus diversions can be found at www.lothianbuses.com .

Business Support

A Support for Business package is in place, devised in consultation with businesses in the area, which includes a local voucher scheme, an ‘open for business’ campaign across a range of media, and a business continuity fund. 

Logistics Hub

A Logistics Hub to support businesses remain operational near Jane Street to help with deliveries and dispatches. Help will also be at hand for residents expecting large deliveries such as appliances or furniture.

Please note that from the weekend of 3/4 December 2022 logistics provision will be relocated between Crown Place and Crown Street to help with deliveries and dispatches. Please get in contact with our teams should you have any specific requirements.

Cycling

Localised works are ongoing to construct the new cycle lanes. As a result, the existing cycle diversion routes will remain in place until completion.

 

Downloads

View Foot of the Walk traffic management plans as of October 2022 (PDFs)