Building the line

Find out more about how we will construct the line to Newhaven via Leith

Construction work on the project commenced in mid-November 2019 and will continue through to late Summer 2022 followed by a period of testing. This will require the closure of some streets and reduced traffic flows on others. You can find out more information on road closures, diversion routes, displaced bus stops and waste collection below. You can download a Construction Phasing Map which gives an overview of the construction timetable. 

Our approach

We are constructing the line using a phased 'one-dig' approach. This means we will not reopen a worksite until all utility and infrastructure works have been completed. By following this approach, the level of disruption to you will be reduced. For example, if your bus stop is displaced, the location of your new bus stop will remain in the same place for the duration of the works.

Additionally, large worksites allow us to be more efficient with our teams on the ground. Should an issue arise where work cannot take place in a specific area, we will have the flexibility to deploy them elsewhere in the worksite. This allows us to avoid unnecessary delays and successfully deliver the project on time.

Our traffic management approach has been jointly approved by members of the city's Traffic Management Review Panel, including Lothian Buses and the emergency services. Emergency access to the site is maintained at all times in the event access is required.

We will always ensure that you are kept aware of any planned works in advance of commencement. This will give you time to modify your normal journey and allow you to get to work, school or elsewhere on time.

Considerate Contractor Scheme

Sacyr Farran Neopul and and Morrison Utility Services both follow the principles of the Considerate Constructors Scheme, which requires a firm focus on outstanding management, efficiency, awareness of local environmental issues, and a genuine consideration for neighbours and the community. 

During the time that the above works are being undertaken, all efforts will be made to minimise disruption and inconvenience to residents and businesses as much as possible. Further details can be found at www.ccscheme.org.uk/

Construction Programme

Constitution Street

Work on building the tram route through Constitution Street began on 18 November 2019             

Work began in two sections:

  • Foot of the Walk to Coatfield Lane – scheduled to be completed by Spring 2021
  • Queen Charlotte Street to Constitution Place – scheduled to be completed by Autumn 2020.

SFN and MUS’ roles involve excavation of the road to allow utility diversions, tracklaying, installation of tram infrastructure, public realm improvements, and heritage and archaeology works. This includes the Robert Burns statue, situated on Baltic Street, which has now been removed is undergoing restoration works, before being returned to a new and improved public complete.

In addition, the South Leith Parish Church wall is currently being taken down and re-built. The memorials on the inner face of the wall will also be removed and protected so that they can be reinstated when the wall is re-built

Further work is scheduled to take place between:

  • Coatfield Lane and Queen Charlotte Street – starting Spring 2021 scheduled to complete in Spring 2022.
  • Constitution Place and Tower Place – starting Autumn 2021, scheduled to complete in Summer 2022.

Traffic Management

Traffic management arrangements have been approved jointly with members of the city's Traffic Management Review Panel, including Lothian Buses and the emergency services, and are now in place. Diversion routes and advanced warning signage have been erected in to help people move around the area with ease.

Throughout this construction period, access is being maintained to Kirkgate House from Laurie Street and to Coatfield Lane from Queen Charlotte Street. The Bernard Street to Baltic Street, Mitchell Street to Maritime Lane and Queen Charlotte Street road crossings remain open. All other sections of Constitution Street are closed to vehicles. 

The project will carefully monitor how the traffic management is working during the construction period.

You can download the traffic management plan and text version for Foot of the Walk to Coatfield Lane.

You can download the traffic management plan and text version for Queen Charlotte Street to Constitution Place.

You can download the 12 and 16 bus service diversion map. 

Constitution Street Parking

In order to enable pedestrian access given the narrow layout of Constitution Street and because the road is closed to traffic there will be no on-street parking during construction.

Please be aware that the City of Edinburgh Council recently undertook consultation on the introduction of a Controlled Parking Zone (CPZ) in the area.

Tower Street and Shore Parking 

On-street parking on the north side of Tower Street is restricted until Summer 2022. The traffic management arrangements for the south side of Tower Street will be maintained and any restrictions will be notified by placing of no waiting cones 24 hours in advance. On-street parking on the west side of the Shore from Bernard Street to Tower Street is also restricted until Summer 2022. These measures are necessary in order to maintain access to residents and businesses to Tower Street via the Shore.

Bike Racks

We are required to remove the bike racks between Maritime Street and Baltic Street as part of the Constitution Street works. We apologies for any inconvenience caused.

Constitution Street Planters

The two large blue planters that were situated on Constitution Street have been moved.

The planters were originally put in place as part of the Leith Programme and have been moved temporarily to an off-street area at the bottom of Constitution Street. They will be stored and maintained at this location until construction on Constitution Street is finished Spring 2021. At this point they will be returned to their original positions.

Construction Site

Fencing has been erected in order to establish the construction site and to allow works to take place.

Communal bins that were situated on Constitution Street have been moved to the nearest side street. The regularity of uplifts will be monitored to ensure the area is kept clean and tidy. If you require a bulk uplift, please contact the Council’s waste service in the usual manner.

 

Leith Walk enabling works

The Leith Walk enabling works involve the removal of parking and loading bays on Leith Walk on the city bound side of the road. During the works, traffic will continue to flow in both directions and bus stops will be maintained on the street, although they may need to be moved a short distance.

The enabling works are required to provide a city bound running lane from Foot of the Walk to London Road which remains open for the duration of the main construction works.  The enabling works involves the removal of certain build outs and the reduction of the footway at some locations. All enabling works are scheduled to be completed early 2020 and will facilitate the main tram construction works which will start on 28 March 2020, with an estimated completion date of Autumn 2021.

Traffic Management

Throughout the enabling period, one lane will be open in each direction with occasional closure of some side streets. Bus services remain unaffected, other than some bus stops being moved a short distance in agreement with Lothian Buses.

Diversion routes and advanced warning signs are in place for information and wayfinding.  The project continues to carefully monitor how the traffic management is working. 

Communal bins that are currently situated on Leith Walk in the affected sections have been moved to the nearest side street. The regularity of uplifts will be monitored to ensure the area is kept clean and tidy.  

Parking and loading

In order to support public transport provision during enabling works there is no on-street parking and loading available within each traffic management section but we will endeavour to be flexible and make space available where possible. 

If we do need to move your bus stop, we will inform you in advance via on street notices. Information will also be available on the Lothian Buses website as well as via the Transport of Edinburgh app. Bus timetables will remain as they are during the enabling works.

Cycling infrastructure 

The traffic managements plans have been agreed in advance as part of the Traffic Management Review Panel process, which included input from cycling and active travel groups, and this unfortunately requires the temporary closure of some cycling infrastructure in this section of works.

The works will benefit the cycling community in the longer term as they are vital to creating the south (city) bound running lane that is needed for the larger section from London Rd to Crown Place. This will allow for guaranteed cycling infrastructure to be accommodated in the longer duration temporary traffic management scheme from Spring 2020 which will create a much safer space for cyclists during the main works.

Leith Walk Planters

The 15 planters that were situated on Leith Walk as part of the previous Leith Programme have been moved to the Easter Road / Duke Street / Lochend Road / Vanburgh Place junction.

Leith Walk Main works

The Leith Walk main works are scheduled to start on 28 March 2020 with a estimated completion date of Summer 2021. During construction, the road will be reduced to one lane heading city bound. 

You can download the traffic management plan and narrative for London Road to Crown Place

Newhaven

Works in the Newhaven area will commence on 6 March 2020. You can find out more information about specific dates and locations in the full phasing map below. 

You can download the Newhaven - Melrose Drive traffic plan.

In addition, you can download the bus diversion map

Waterfront area

Works in the Waterfront area from will commence on 13 March 2020 outside Ocean Terminal. You can find out more information about specific dates and locations in the full phasing map below. 

You can download the traffic management plan or text version and the bus diversion map for this area. 

Full construction programme

Full phasing map (91KB)

You can view a breakdown of the construction programme along with traffic management plans in the Proposed Timelines section of the website.

Displaced bus stops
During the works, it is likely that your usual bus stop will be relocated. We are currently finalising bus diversion routes in partnership with our colleagues at Lothian Buses. We will publish information here also send notification to everyone who is signed up to our mailing list when it becomes available. For real-time information once the work commences you can check the 
Lothian Buses website or download the Transport for Edinburgh app.

Waste collection

For those who live on streets where works will take place, it is likely that bin locations and pick up points will change. We are currently finalising the location of residential waste collection and will post information here when it becomes available. If you wish to be kept informed, please sign up to receive updates here.

Updated permanent designs

We have updated the permanent design drawings to take consideration of feedback received from the community. These designs, however, should be viewed as indicitive as we may need to make some minor changes as we proceed through the project. Updates will be posted here and communicated to you via email. Should you wish to be kept up to date, you can sign up to our mailing list.